Shri K.K Sharma, Advisor to Hon’ble Governor, J&K State today reviewed the progress of various important projects being executed by J&K ERA under the ongoing JKUSDIP (Jammu and Kashmir Urban sector Development Investment Programme ) funded by Asian Development Bank at J&K ERA Office , Rambagh Srinagar.
 
Dr. Raghav Langer, Chief Executive Officer, J&KERA while giving PowerPoint presentation of the ongoing JKUSDIP (Jammu and Kashmir Urban Sector Development Investment Programme ) informed that out of the total of 53 sub-projects works on 43 sub-projects which include construction of mechanized car parking facility at KMDA, Srinagar and at city chowk super bazaar, Jammu, Vikram Chowk flyover at Jammu, 1st phase of Jehangir chowk-Rambagh Flyover, New Mehjoor Bridge at Jawahar Nagar, Srinagar, 3 landfill cells at municipal Landfill site , Achan, Srinagar besides providing of equipments to PHED and SMC while as work on remaining 10 sub- projects is under execution at present.
 
He said that 99% physical progress has been achieved on the construction of Rawalpora-Chanapora storm water drainage sub-project with work on laying of drainage network and construction of two main pumping stations already complete. He added that 76% physical progress has been achieved on the construction of Storm Water drainage sub-project along the national highway byepass at Athwajan and 87% progress has been achieved on the laying of 18Kms raw water pipeline from upper reaches of Doodhganga at Nauhara to Kralpora and balance portion of these works had to be re-tendered due to the non-performance of the contractors and these works will be completed by May, 2019.
 
Giving details about the progress of work on the construction of Jehangir-Chowk -Rambagh flyover CEO, ERA informed that 84% physical progress has been achieved on the project as a whole and said that as per the revised pert chart submitted for the pending works of the flyover contractor has committed to complete the balance work on the sub-project by May, 2019. Hon’ble Advisor appreciated the support being provided by the District Administration, Srinagar to JKERA for smooth execution of work on the flyover. He also directed JKERA to ensure that the non-performing contractors be got blacklisted and appreciated the fact that JKERA under loan I and Loan 2 has been been able to create state of art key public assets with the financial assistance of Asian Development Bank.
 
Later Advisor K.K Sharma visited the constructions sites of Jehangir Chowk Rambagh Flyover and Grade Separator at TRC,Srinagar during which he directed the engineers and contractor to further speed up the pace of work to ensure that timelines are strictly complied with .
 
Meeting was also attended by Dr, Shahid Iqbal Choudhary, Deputy Commissioner, Srinagar, Tahir Geelani, S.S.P Traffic, Srinagar, Ashok Kumar, Chief Engineer, I&FC, , Adbul Wahid Chief Engineer, PHE,Kashmir, Sami Arif , Chief Engineer, R&B, Kashmir, Hashmat Qazi, Chief Engineer, EM&RE, Kashmir, Showkat Wani, Director, Kashmir, J&KERA, Nazir Ahmad Baba, Additional Commissioner, Srinagar Municipal Corporation and other senior officers of line departments and J&KERA,