Approach Road Achhan Landfill Site
Construction of Approach Road at Achhan Landfill Site *
Leachate Treatment Plant Unit I

Loan:

2331-IND
Category: Engineers Design
Location: Kashmir Urban SWM
Districts Passing:

Constituency Passing:

Status: Works Completed
ERA Ref: Type:Works Mode: NCB
ERA Pac ID: 0201.2
PCSS No: 0001-2
Scope of Work: 0.443 Km
Contract Cost in Rs crore: 2.2037
Dynamic Cost in Rs crore: 2.47
Contractor Details Gousia Road Construction
DDR Approve Date
DPR Approve Date
IFB Issue Date (Last) 05 September 2007
Technical BID Open Date
Financial BID Open Date
Letter of Acceptance to contractor (LOA) 21 May 2008
Date of Signing of Contract 21 May 2008
Date of Start of Work (NTP) 18 June 2008
Completion Period (6 Months)
Completion Date as per Contract 12 October 2008