ERA Projects
J&K ERA Main Logo
Govt. of Jammu and Kashmir
  Jehlum Tawi Flood Recovery Project (JTFRP) | Search | | Admin |
Project Details
GO BACK
Equipment PHED Srinagar Lot5
Supply & delivery of equipment use in Public Health Engineering Department, Srinagar - Lot 5

Loan:

2925-IND
Category: Equipment
Location: Kashmir Urban Equipment
Districts Passing:

Constituency Passing:

Status: Works Completed
ERA Ref: Type:Works Mode: NCB
ERA Pac ID: 526
PCSS No: temporary-112
Scope of Work:
Contract Cost in Rs crore: 6.27
Dynamic Cost in Rs crore: 6.27
Contractor Details TATA Motors
DDR Approve Date
DPR Approve Date
IFB Issue Date (Last)
Technical BID Open Date
Financial BID Open Date
Letter of Acceptance to contractor (LOA) 27 June 2016
Date of Signing of Contract 27 June 2016
Date of Start of Work (NTP)
Completion Period (4 Months)
Completion Date as per Contract 27 October 2016