Naraspora-Budgam Bridge
Bridge at Naraspora Budgam
Completed view of the BRidge. only approaches have to be constructed.

Loan:

2151-IND
Category: Forced Account
Location: Kashmir Transport Bridges
Districts Passing:

Constituency Passing:

Status: Works Completed
ERA Ref: Type:Works Mode: Force Account
ERA Pac ID: 0017
PCSS No: 0017
Scope of Work: 22 Mts
Contract Cost in Rs crore: 1.3
Dynamic Cost in Rs crore: 1.31
Contractor Details JKPCC
DDR Approve Date
DPR Approve Date
IFB Issue Date (Last)
Technical BID Open Date
Financial BID Open Date
Letter of Acceptance to contractor (LOA) 17 February 2006
Date of Signing of Contract 17 February 2006
Date of Start of Work (NTP) 14 June 2007
Completion Period (24 Months)
Completion Date as per Contract 31 October 2007