Strengthening of Existing System Rising Mains (Phase-II)
Replacement of Rising mains, laying new rising mains & gravity mains in various parts of Jammu city [Strengthening of existing system (Phase-II)

Loan:

2151-IND
Category: Engineers Design
Location: Jammu Urban Water Supply
Districts Passing:

Constituency Passing:

Status: Works Completed
ERA Ref: Temp17 Type:Works Mode: LCB
ERA Pac ID: 0055
PCSS No: 0032
Scope of Work: 250-100 dia 25 km
Contract Cost in Rs crore: 7.05
Dynamic Cost in Rs crore: 4.29
Contractor Details Electrosteel Casting Ltd
DDR Approve Date 27 October 2005
DPR Approve Date
IFB Issue Date (Last) 12 August 2006
Technical BID Open Date 18 September 2006
Financial BID Open Date 12 October 2006
Letter of Acceptance to contractor (LOA) 15 January 2007
Date of Signing of Contract 10 February 2007
Date of Start of Work (NTP) 22 February 2007
Completion Period (15 Months)
Completion Date as per Contract 21 May 2008
 
Length of Pipe Line: - 25.14KmTotal Area to be served: -20 Sq. km.Population served: - 3,00,000 soulsAreas benefitted: - Channi Himmat, Sunjwan, Belicharana, Chak Bija, Apna Vihar, Babliyana, Nanak Nagar, Karan Baghetc. in Jammu east.