Loan:
|
2925-IND |
| Category: |
Engineers Design |
| Location: |
Jammu Urban Water Supply |
| Districts Passing: |
|
Constituency Passing: |
|
| Status: |
Works Completed |
| ERA Ref: |
JKUSDIP Jammu/WS-01 Type:Works Mode: NCB |
| ERA Pac ID: |
370 |
| PCSS No: |
0015-03 |
| Scope of Work: |
7 nos. Tubewells |
| Contract Cost in Rs crore: |
13.01 |
| Dynamic Cost in Rs crore: |
13.01 |
| Contractor Details |
Hanuman Tube well |
| Date of Signing of Contract |
|
| Date of Start of Work (NTP) |
01 July 2013 |
| Completion Period |
(52 Months) |
| Completion Date as per Contract |
01 July 2017 |