Index Page
J&K ERA Main Logo
Govt. of Jammu and Kashmir
   
NEWS

Dated 17 January 2019
Complete projects within agreed timelines: CEO ERA
Dr. Raghav Langer, Chief Executive Officer, J&K ERA today reviewed the progress of various projects funded by the World Bank/ Asian Development Bank in a high level meeting which was attended by the officers of SMC , R&B , Kashmir, PHED, Kashmir , JKPCC, UEED
 
Peerzada Hafizullah Shah , Commissioner, SMC informed CEO, ERA that under the component of urban flood management infrastructure of JTFRP(Jhelum Tawi Flood Recovery Project) work on construction of 49 storm water pumping stations which is estimated to cost Rs 102 crores has been awarded in the Dec,2018 and work on the sub-project which primarily involves the installation of electromechanical equipments along with requisite civil works will be completed within 18 months. He further said that preparation of DPR for the construction of Nadroo drainage scheme will be completed by the next week while as for Bonpora scheme DPR is under preparation.CEO directed SMC to expedite the process of procurement of mobile waste water testing equipments for monitoring of water of pumping stations and other equipments that are to be provided to the SMC under JTFRP.He further directed SMC to prepare a design for the SCADA building in consultation with Dept. of Disaster Management Relief Rehabilitation and Reconstruction which is proposed to be housed in the Composite Central Control Room that will also include proposed SEOC (State Emergency Operations Centre) at Humhama.
 
Harkewal Singh , General Manager , JKPCC informed that ESIA (Environment and Social Impact Assessment) for the new proposed hospital complex at L.D Hospital which is estimated to cost Rs 74 crores is under preparation and expected to be completed by 25th , January,2019 along with other necessary tests that are required to be done prior to start of work on ground. G. M JKPCC further informed that work on construction of Higher secondary school at Jawahar Nagar and 8 bridge and 3 road sub-projects in Baramulla, Pulwama, Anantnag and Shopian Districts is also underway. CEO JTFRP directed JKPCC to strictly follow the quality parameters during execution of works and also get the tests conducted at site verified from the third party.
 
Giving details about the progress of the component of strengthening of critical Infrastructure the Mushtaq Ahmad Shagoo, S.E R&B, Kashmir which is PIU for the component informed that bids for the construction of 3 buildings at Govt. Degree college, Bemina, GDC Anantnag , GDC, Bijbehara are being evaluated while as the bid evaluation process for the construction of 120 bed new in-patient , operation theatre and spinal care centre at Bone and Joint Hospital, Barzulla has been completed and referred to contract committee of R&B for necessary approval.He added that tenders for the construction of 35 school buildings in Kashmir, division have also been issued out of which evaluation process for 27 has been completed while as tenders for the construction of 5 bridges have been tendered out of which 01 is ready for award while as DPRs are being prepared for the 12 road sub-projects in Kashmir.
 
Later on Dr. Raghav reviewed the progress of under execution ADB funded projects in Srinagar. Showkat Wani, Director Kashmir , J&KERA informed that as on date 86% physical progress has been achieved on Jehangir-chowk Rambagh flyover project.He further said that the construction of downward ramp at Alloch-Bagh is already complete whereas construction of upward ramp at Rambagh is in full swing. While as in the 3rd and final phase of the project from Jehangir-Chowk to Amar Singh College crossing focus is being given on the construction of heavy structural components like erection of pre-cast concrete girders followed by laying of concrete slabs. He added that work on Grade Separator at TRC is underway with 75% physical progress achieved on it. As regards progress of Storm water drainage projects it was said that construction of Storm water drainage system for Rawalpora-Chanapora area having a catchment area of 284.76 hectares is also nearing completion.
 
Preparedness for forthcoming JKIDP( Jammu and Kashmir Infrastructure Development programme) to be funded by Asian Development Bank was also discussed during the course of the meeting. Chief Engineer , PHED was informed that the projects for augmentation of water supply by 10 MGD in Greater Srinagar increasing service levels of water supply as per CPHEED norms at a tentative cost of Rs 270 crores have been provided under JKIDP . Accordingly under the sewerage sector projects for 30 MLD new STP , upgradtion of existing 04 STPs and laying of sewerage costing Rs 220 crores have also been provisioned for under the JKIDP.Further Chief Engineer UEED, J&K was directed to share the sewerage network drawing of the service areas of UEED, LAWDA and NBCC with the Hydraulic section of J&KERA CEO,ERA directed the officers of all the line departments present in the meeting to ensure completion of all projects within the agreed timelines to prevent cost overruns.
Meeting was also attended by Satinder Singh Rana, Chief Engineer, UEED/ Director Safeguards JKERA , Abdul Wahid,Chief Engineer, PHED, Kashmir, Showkat Wani Director Kashmir J&KERA, J&K, Iftikhar Ahmad Hakim ,Director Planning and Coordination, JTFRP, Khalid Ahmad Director, Technical, JTFRP, Amir Ali Director Disaster Management JTFRP, Suresh Koul, Director, Finance, J&KERA, Tasawuf Ahmad , Chief Accounts Officer , SE, R&B, Kashmir, JTFRP and other senior officers of JKERA, UEED, PHED and SMC
Mohammad Azhar, PRO Kashmir
 
Dated 15 January 2019
Strengthening of SDRF and F&ES through JTFRP World Bank Funded Project: CEO ERA
Strengthening of SDRF and F&ES through JTFRP World Bank Funded Project: CEO ERA
 
State of the art search and rescue equipments are being procured for strengthening of Disaster Management Operations in J&K State under World Bank funded JTFRP Project. This was informed by Dr. Raghav Langer, Chief Executive Officer, Economic Reconstruction Agency/JTFRP in a meeting chaired by V.K Singh Director General SDRF, HG, CD and Fire and Emergency Services. The meeting was also attended Aamir Ali Director Disaster Management and Tasawuf Amin Director Finance JTFRP
 
These rescue Equipments are being procured under Component 5 of JTFRP which includes procurement of rescue equipments for State Disaster Response Force (SDRF), Fire and Emergency Services. 30 boats have already been procured for SDRF and process for procuring 28 boats has been completed. The equipments for SDRF includes Collapsed Structure Search and Rescue Equipments (CSSR) and water rescue equipments such as Electric Angle Cutter, Regulator Gas Cutter, Electric Circular Saw etc, 5 snow cutting machines, 16 rescue vehicles, 22 lighting towers and generators. The equipments for Fire and Emergency Services includes 17 multipurpose fire tenders, 9 regular fire tenders, 17 medium quick response vehicles, hydraulic spreaders, cutters, combi tools, ramps, hydraulic jacks, fire entry suits, fire proximity suits, breathing apparatus, water gel blankets, under water cameras, floating pumps and portable dewatering pumps. The equipments are being procured at an approximate cost of Rs. 40 crores. The process of procuring is at different stages of completion. CEO ERA/JTFRP apprised that to handle these high end equipments specialized training can be imparted that can be in house or external.
 
Dr. Langer informed that the equipments are being procured under JTFRP Project and will strengthen the capabilities of SDRF Fire & Emergency Services in conduct of rescue operations in case of any calamities like earthquakes, landslides, floods etc. Further, the team also inspected the rescue equipments available with SDRF at their Battalion Headquarters at Gandhi Nagar. Commandant SDRF Rashmi Wazir, Staff Officer with Commandant General Mohammed Shabir and other officers were also present during the inspection. The staff demonstrated the functioning and uses of various rescue equipments that includes Bamboo Raft, Multi Purpose Rope, Inflatable Rubber Boat, Fire Entry Suit, Water Mist, Diving Suit, Reciprocating and Carbide Chain Saw.
 
 
Makarand Mehta
 
Dated 22 December 2018
Rs. 4.53 crores being spent on development of Handicraft clusters under World Bank funded JTFRP.
Consultancy support for the development of Embroidery and Papier Machie crafts are being developed at Noor Bagh and Zadibal at Srinagar respectively at a cost of Rs. 2.39 crores and Rs. 2.18 crores respectively.
 
This was stated to Dr. Raghav Langer Chief Executive Officer J&KERA / JTFRP during his visit to the said handicraft clusters here today. The project has been taken up under restoration and strengthening of livelihood component of the World Bank funded Jhelum Tawi Flood Recovery Project and Department of Industries and Commerce is the Project Implementation Unit for the component. CEO ERA / JTFRP was informed by officials of Handicraft Department that so far comprehensive skill assessment of the artisans skilled in the traditional crafts of Embroidery (crewel, chain-stitch) and Papier Machie has been done and artisan have been categorized according to their level of skill by the consultants who have been engaged for the purpose and now the focus is being given on the upgradation of the skills of the artisans and for which recently a workshop was organized for the artisans wherein they were imparted latest trainings on product design and color schemes to be adopted while designing a product. It will be followed by providing artisans with improved market linkages with assured supply order worth Rs 3 crores for each provide them with platforms to participate and exhibit their crafts in major exhibitions. The creation of artisan database and creation civil infrastructure in the said handicrafts clusters areas is also included in the overall project.
 
Later CEO ERA / JTFRP also visited Solina Silk Factory wherein Officer was shown various sections of the Filature which has been established way back in 1939. A consultancy services for preserving the heritage value of the unit its landscaping and exploring opportunities for setting up of the Haat in the premises is also being carried out under the said project.
 
Ghulam Qadir, General Manager, Joinery Mill , Pampore , Nodal Officers of JTFRP/ handicrafts department accompanied CEO ERA/JTFRP during the visit.
 
 
Muhammad Azhar, Public Relations Officer
 
Dated 30 October 2018
Contractor for Jehangir Chowk – Rambagh Expressway corridor penalized.
Contractor undertaking the work on Jehangir Chowk –Rambagh Expressway corridor is to be penalized with an amount of Rs 1.25 crores approximately for delaying the work on Rambagh Flyover mega –project which is coming up in the heart of city centre.
 
Dr. Raghav Langer , Chief Executive Officer has stressed that any further delay on part of the contracting agency will not be tolerated and shall be dealt with severely. The construction agency has been directed to strictly adhere to the timelines given for the completion of the project. CEO, ERA has directed the contractor to ensure that the 2nd phase of the mega project from Rambagh to Aloochi Bagh is completed by 31st , Dec, 2018 while as 3rd phase from Allochi –Bagh to Jehangir Chowk be completed structurally by 15th March , 2019 with black topping to be completed by 15th, May, 2019.
 
Dr. Raghav said that any dilly-dallying tactics on part of the contracting agency shall lead to further penalization in accordance with the contract clauses and black listing of the construction agency. He added that work on the construction of grade separator at TRC, Srinagar has also been put on the watch list and performance of the construction agency is being closely scrutinized and similar penal action would follow if the work on project is not expedited and timelines given to the contractor are not met.
 
 
 
Mohammad Azhar, PRO
 
Dated 26 October 2018
Modalities for Establishment of Emergency Operations Centres under JTFRP discussed.
Modalities for the establishment of EOC (Emergency Operations Centre) under the ongoing World Bank funded Rs 1500 crore Jhelum Tawi Flood Recovery project was discussed here today during a meeting that was chaired by Dr. Raghav Langer, Chief Executive Officer, J&K ERA and also attended by visiting team of World Bank that was on 5 day visit to the valley for mid-term review of JTFRP.
 
During the meeting it was proposed that two pronged approach needs to be adopted for the purpose by initially setting up the Emergency Operations Centre on Cloud based platform which will later on be further strengthened by setting up of (2) physical Emergency Operations centre at Srinagar and Jammu and subsequently by setting up of EOC’s at all the district levels. However the Cloud based EOC will continue to support the physically established EOC;s and will also serve as backup in case of emergencies’. The proposed EOC will be equipped with the all the necessary equipments like Desktop computers, printers and manned by disaster management and I.T professionals. The EOC’s will operate on the basis of customized software that will have important emergency response features like organizational registry, tracing the missing persons, tracking the displaced families, shelter tracking, volunteer management etc.
 
CEO, ERA directed the concerned officers to obtain the list of registered hardware / software vendors from the department of I.T and also directed the Disaster Risk Assessment consultancy of JTFRP to come up with detailed costing for the project and also prepare the further road map for the project at an earliest.
 
The meeting was also attended by Iftikhar Hakim, Director Planning and Coordination, JTFRP, Khalid Iqbal, Director Technical, JTFRP, Aamir Ali, Director Disaster Management and other officers’ of JTFRP and ERA
 
 
Muhammad Azhar, Public Relations Officer
 
Dated 23 October 2018
World Bank funded Rs 1500 crore Jhelum Tawi Flood Recovery Project reviewed.Additional Block of Bone and Joint Hospital to com
Chief Executive Officer, J&KERA today reviewed the progress of Rs 1500 crore World Bank funded JTFRP (Jhelum Tawi Flood Recovery Project) in presence of Khursheed Ahmad Shah, Commissioner Secretary Public Works department and the visiting team of World Bank headed by Deepak Singh, Task Team Leader and comprising of several other senior officers of World Bank.
 
Giving out details about the progress of Public Works component of the project it was informed by the nodal officer, PWD, Kashmir that the component involves the sub-components of Health, Higher Education, High education and rehabilitation of (5) fire service stations. He said under the health sub-component Rs 89 crores have been earmarked for the construction of state of art 120 bed capacity additional block at Bones and Joints Hospital, Barzulla, Srinagar which will be equipped with the latest medical equipments, operation theatres, HVAC system, fire and maintenance and other latest facilities.. Under the Higher education sub-component Rs 34 crores have been allocated for the construction of additional blocks at Govt Degree College, Bemina, GDC Anantnag, GDC Bijbehara, Amar Singh College Srinagar and works worth Rs 23 crores have already been tendered. It was also said that under high education 53 schools are proposed to be constructed across the Kashmir valley for which an allocation of Rs 35 crores has been kept and tenders for construction of 7 schools have already been issued and tenders for remaining shall be issued by end of Nov, 2018.Further 8 Bridges are proposed to be constructed in Kashmir for which an allocation of Rs 70 crores has been kept and tenders for two bridges have already been floated. Similarly 12 road projects having an approximate length of 117 Kms are proposed to be constructed in Kashmir Division.
 
Sudhir Shah Chief Engineer, R&B, Jammu while giving out details about Jammu division said that 24 school buildings are proposed to be constructed in Jammu division for which an allocation of Rs 15 crores has been kept and tendering process for these will be completed by 15th, Nov, 2018.He further said that 17 road projects having a cumulative length of 176 kms are also proposed to be taken up.
 
CEO, ERA directed the officers present in the meeting to expedite the process of preparation of due diligence documents so that works are tendered out and executed on ground at an earliest. He also directed that due care be taken of the architectural and heritage aspects while preparing designs for projects like construction of additional blocks at Amar Singh College so that the newly constructed blocks merge aesthetically with the existing buildings in the campus. It was further directed that EOI (Expression of Interest) for assessment of structural stability and detailed design for retrofitting of (5) fire stations in Kashmir and some other structures be prepared and issued at an earliest.
 
Meeting was also attended by Sami Arif, Chief Engineer,R&B Kashmir, Iftikhar Ahmad Hakeem Director Planning and Coordination JTFRP, Khalid Iqbal Director Technical, JTFRP, Ajaz Ahmad Bukhari, Executive Engineer, division 2nd ,Nodal officers of Bone and Joint Hospital, L.D Hospital among others
 
Muhammad Azhar, Public Relations Officer
 
Dated 22 October 2018
World Bank Team Arrives in Valley.
World Bank Team led by Task Team Leader Deepak Singh and comprising of several senior officers of India country office arrived here today in Srinagar to review the progress of World Bank funded Rs 1500 crore Jhelum Tawi Flood Recovery project which aims to revive the basic infrastructure that had been damaged due to the devastating floods of 2014.
 
The team upon its arrival in Srinagar attended the meeting at Civil Secretariat, Srinagar which was held under the chairmanship of Shri Rohit Kansal, Principal Secretary Planning, Development and Monitoring Department who apprised the visiting team about the progress achieved on Jhelum Tawi Flood Recovery .Dr. Raghav Langer, Chief Executive Officer, JKERA also attended the meeting.
 
Later in the day Dr. Raghav Langer chaired the meetings wherein the visiting team was apprised about the progress achieved on Urban Flood Management and Restoration and Strengthening of livelihood components of the JTFRP. The meetings were also attended by Peerzada Hafizullah, Commissioner, Srinagar Municipal Corporation, Javid Iqbal, Managing Director, J&K Industries and Commerce department which form the project implementation units of JTFRP along with the Public Works Department. The meetings were also attended by other senior officers of JTFRP unit of ERA.
 
 
 
Mohammd Azhar, PRO
 
Dated 20 October 2018
CEO ERA inspects Rawalpora- Chanapora Storm Water Project
97% progress achieved on the project, Projects to benefit more than 60,000 thousand souls
 
J&K ERA has achieved 97% physical progress on the Rawalpora- Chanapora mega storm water drainage project which is being constructed by J&K ERA with cost of Rs 165 crores under its Asian Development Bank funded JKUSDIP (Jammu and Kashmir Urban Sector Development Investment Programme).
 
This was informed to Dr. Raghav Langer, CEO, ERA during his visit to the site. Zulfiqar Beigh, Project Manager, Hydraulic , JKERA said that the project will benefit the catchment area of 284.75 hectares along the National highway byepass which include localities from Rangreth to Chanapora bridge and will benefit around 60,000 souls living in the localities. He said work on civil components of laying of main and sub-main drainage network has already been completed as well as construction of (03) main pumping stations along with the installation of electromechanical components which are equipped with submersible pumps each having discharge capacity of 25 cusecs, 40 cusecs and 37 cusecs respectively which can work even in inundated conditions. These include one at Afandi bagh for zone I of the catchment area and main pumping stations at Madina Enclave for zone II and third MPS at Alamdar colony for zone III of the catchment while as work on one IPS (Intermediate pumping station) near check yayil near which is required for zone III of the project couldn’t be taken up so far due to some land acquisition issues.
 
CEO, ERA directed the concerned officers to immediately submit the formal proposal regarding the land acquisition issue involved in the construction of intermediate pumping station so that the issue is taken up with the concerned quarters for its resolution. CEO, ERA also directed consultants to prepare the proposal for automation of the storm water drainage projects completed by ERA through SCADA system so far so that same may be proposed in the forthcoming JKIDP (Jammu and Kashmir Infrastructure Development Project) funded by Asian Development Bank.
 
 
Muhammad Azhar, PRO
 
Dated 17 October 2018
CEO ERA inspects progress of work on transport projects in Srinagar city
Dr. Raghav Langer (IAS) Chief Executive Officer J&KERA today undertook on-site inspection of various transport projects being executed by J&KERA in the Srinagar city under the ongoing Asian Development Bank funded JKUSDIP (Jammu and Kashmir Urban Sector Development Investment Programme).
 
During inspection of work on Jehangir –Chowk –Rambagh flyover project . Showkat Wani , Director Kashmir , JKERA informed that under phase-I of the project etween comprising of Amar Singh college to Barzulla Bridge has already been completed in May , 2018 and one way traffic on the stretch is plying which has decongested the traffic on the said road stretch underneath to a great extent and presently work on 2nd phase of the project between Rambagh to Allochi-Bagh stretch has been further accelerated and more than 80% physical progress has been achieved. CEO ERA directed contractor to ensure that phase –II of the project is completed and made motarable by 31st Dec, 2018.While giving out details about 3rd- phase of the project between Amar Singh College to Jehangir Chowk it was informed that as on date 50% progress has been achieved and structural component of the phase is expected to be completed by March-2019.
 
Later CEO, ERA inspected progress of work on grade separator near TRC where he was informed that 60% physical progress has been achieved on the project as a whole and presently work on construction of ramps on Sonawar- Linz and JK Bank Corporate limbs are in full swing.CEO ERA directed contractor to mobilize additional man and machinery to ensure the completion of work by Dec, 2018 and March, 2019 respectively for both limbs.
 
It was also directed by CEO that concerned engineers and consultants of ERA will on daily basis monitor the progress of these works in case of laxity on part of the contractor penalty and other penal provisions in the clause shall be invoked . The CEO reiterated that these projects be completed as per the agree timelines as already excessive dealy has happened in the completion of these vital projects.
 
The concerned contractor for the flyover project raised the issue of diversion of traffic between Naaz Crossing to Jehangir Chowk for undertaking works in this stretch regarding which the CEO directed ERA officials to submit a detailed site plan within timelines so that the same can be taken up with IGP Traffic, Srinagar.
 
Besides Director Kashmir, JKERA, Sheikh Javed, Project Manager, Transport , J&K ERA. Team Leader, DSC and other officers of JKERA and consultants accompanied CEO ERA during the site visit
Muhammad Azhar, Public Relations Officer, JKERA
 
Dated 16 October 2018
Dr. Raghav Langer assumes charge of Chief Executive Officer
Dr. Raghav Langer (IAS) Officer of 2009 batch today assumed the charge of Chief Executive Officer, J&K ERA.
 
The Officer has wealth of experience in the area of infrastructure projects and has also served as Chief Executive Officer, PMGSY, Programme Director of Namami Gange, Project Director for World Bank funded Peri- Urban Water Supply Programme in Uttrakhand. On assuming the charge of Chief Executive Officer, JKERA, Dr Raghav was accorded a warm welcome by officers and staff of J&K ERA.
 
CEO. ERA was briefed about the organizational structure of JKERA. Later in the day CEO ERA was chaired a meeting wherein he was informed about physical and financial progress of various mega projects which are presently being executed by J&KERA under its ongoing Jammu Kashmir Urban Sector Development Investment Programme (JKUSDIP) funded by Asian Development Bank (ADB). Meeting was also attended by Showkat Wani, Director, Kashmir, JKERA, Suresh Kaul, Director, Finance, JKERA, Zulfiqar Beigh Project Manager, Hydraulic, Kashmir, Javed Sheikh, Project Manager, Transport, Kashmir and other senior officers of JKERA
 
 
 
Muhammad Azhar, PRO Kashmir
 
Previous Next
<<More News>>