Sidhra-Surinsar-Mansar Road
Dated: 12 April 2009
KM 0/0 near NH-1 Byepass (DBM in Progress)
Work on DBM Started on 3-March-2009. this is the starting point of Road near Sidhra
 
Dated: 12 April 2009
BT in progress(KM 4/500)
BT in progress at KM 4/500,as on 12-04-2009
 
Dated: 12 April 2009
Bridge-03
Work in progress at Bridge No.3 on Sidhra-Surinsar-Mansar Road.Photo taken on 12-April-2009
 
Dated: 12 April 2009
Bridge -02
Bridge No.2 on Sidhra-Surinsar Road
 
Dated: 12 April 2009
Bridge-01
Work in progress on Bridge No.1 on Sidhra-Surinsar-Mansar Road.Photo taken on 12-April-2009
 
Dated: 14 March 2009
Completed View of Papchan Bridge
Complete view of Main bridge from a distance of 150 meters. the bridge is complete and work on approaches is under progress.
 
Dated: 14 March 2009
First Approaches to Papchan Bridge
Project Varitions in terms of extended work in Approaches
 
Dated: 14 March 2009
Land Acquisition in Progress
Collector ERA Shri. Bhat distributing Land acquisition cheques to stake holders.
 
Dated: 31 January 2009
Baribrahmana-Bishnah Road
Bari Brahmna Bisnah Road District Jammu – Length 6.5 Km (Double Lane) work completed in April 2009
 
Dated: 18 December 2008
Site Visit by Advisor to CM
Advisor to HCM Shree. C. Phonsog conducted site visit of this package on 18 dec 2008
 