Wanpoh-Chawalgam-Aharbal Road
|
|
Dated: 17 June 2008
|
|
Breatwalling in Progress
|
|
|
|
The Site Visit Conducted by ERA Experts
|
|
|
|
Dated: 17 June 2008
|
|
Completed view of the Bridge
|
|
|
|
Site Visit Conducted by ERA Experts Head Office
|
|
|
|
Dated: 17 June 2008
|
|
Megdamisation of KM 8-11
|
|
|
|
Site Visit Conducted by ERA Experts Head Office
|
|
|
|
Dated: 17 June 2008
|
|
Megdamisation of KM 8-11
|
|
|
|
Site Visit Conducted by ERA Experts Head Office
|
|
|
|
Dated: 17 June 2008
|
|
Widening of Road in Progress
|
|
|
|
Site Visit Conducted by ERA Experts Head Office
|
|
|
|
Dated: 17 June 2008
|
|
Qulaity Check of Mechdam Used
|
|
|
|
Site Visit Conducted by ERA Experts Head Office
|
|
|
|
Dated: 20 May 2008
|
|
Road with BT Surface Near Wuyan
|
|
|
|
The least populated area done sucessfully without any bottlenecks
|
|
|
|
Dated: 12 May 2008
|
|
clarrifluculators at Doodhganga
|
|
|
|
Work on clarrifluculators in progress as recorded on 12 may 2008
|
|
|
|
Dated: 12 May 2008
|
|
Completed view of the Bridge
|
|
|
|
The bridge has been completed sucessfully for motarable traffic
|
|
|
|
Dated: 12 May 2008
|
|
Land Acquisition required for the Bridge
|
|
|
|
The bridge is complete by 12 may 2008. Land acquistion required for overall completion
|
|
|