Intake Boria Tanks Jammu East (Lot 1)
|
Dated: 01 January 2010
|
Intake Boria Project
|
|
Intake bohria completed by J&K ERA and commissioned on
|
|
Dated: 30 November 2009
|
Sofshali Bridge
|
|
Sofshali Bridge
|
|
Dated: 30 October 2009
|
Natipora-Nowgam-Newa Road
|
|
23.79 Km road completed and handed ovet to R&B Deptt
|
|
Dated: 05 October 2009
|
Sangrama Sopore Road
|
|
27.3 Km road completed and handed over to R&B Deptt
|
|
Dated: 01 October 2009
|
Thajiwara Shangus Road
|
|
Thajiwara Shangus Road
|
|
Dated: 30 September 2009
|
wanpoh Chawalgam Aharbal Road
|
|
42.7 Km Road Completed and handed over to R&B Deptt
|
|
Dated: 02 September 2009
|
Bridge Complete
|
|
Completed view of the BRidge. only approaches have to be constructed.
|
|
Dated: 02 September 2009
|
Bridge Trafficable
|
|
Completed view of the Bridge. Traffic Plying on the bridge from Aug-2009
|
|
Dated: 02 September 2009
|
Retaning Walls
|
|
Constrcution of Retaining walls along the roadsite, as per design.
|
|
Dated: 02 September 2009
|
Retaining wall and Drain
|
|
Drain and Retaining walls, work in Progress.
|
|
|