                   Intake Boria Tanks Jammu East (Lot 1)
                  
                
                 | 
             
          
            
              | 
                Dated: 01 January 2010
                  
                   | 
               
            
              | 
                 Intake Boria Project
                  
                   | 
               
            
              | 
                
                  
                  
                   | 
               
            
              | 
                 Intake bohria completed by J&K ERA and commissioned on 
                  
                   | 
               
            
              | 
                  
                  
                   | 
               
            
            
              | 
                Dated: 30 November 2009
                  
                   | 
               
            
              | 
                 Sofshali Bridge
                  
                   | 
               
            
              | 
                
                  
                  
                   | 
               
            
              | 
                 Sofshali Bridge
                  
                   | 
               
            
              | 
                  
                  
                   | 
               
            
            
              | 
                Dated: 30 October 2009
                  
                   | 
               
            
              | 
                 Natipora-Nowgam-Newa Road
                  
                   | 
               
            
              | 
                
                  
                  
                   | 
               
            
              | 
                 23.79 Km road completed and handed ovet to R&B Deptt
                  
                   | 
               
            
              | 
                  
                  
                   | 
               
            
            
              | 
                Dated: 05 October 2009
                  
                   | 
               
            
              | 
                 Sangrama Sopore Road
                  
                   | 
               
            
              | 
                
                  
                  
                   | 
               
            
              | 
                 27.3 Km road completed and handed over to R&B Deptt
                  
                   | 
               
            
              | 
                  
                  
                   | 
               
            
            
              | 
                Dated: 01 October 2009
                  
                   | 
               
            
              | 
                 Thajiwara Shangus Road
                  
                   | 
               
            
              | 
                
                  
                  
                   | 
               
            
              | 
                 Thajiwara Shangus Road
                  
                   | 
               
            
              | 
                  
                  
                   | 
               
            
            
              | 
                Dated: 30 September 2009
                  
                   | 
               
            
              | 
                 wanpoh Chawalgam Aharbal Road
                  
                   | 
               
            
              | 
                
                  
                  
                   | 
               
            
              | 
                 42.7 Km Road Completed and handed over to R&B Deptt 
                  
                   | 
               
            
              | 
                  
                  
                   | 
               
            
            
              | 
                Dated: 02 September 2009
                  
                   | 
               
            
              | 
                 Bridge Complete
                  
                   | 
               
            
              | 
                
                  
                  
                   | 
               
            
              | 
                 Completed view of the BRidge. only approaches have to be constructed.
                  
                   | 
               
            
              | 
                  
                  
                   | 
               
            
            
              | 
                Dated: 02 September 2009
                  
                   | 
               
            
              | 
                 Bridge Trafficable
                  
                   | 
               
            
              | 
                
                  
                  
                   | 
               
            
              | 
                 Completed view of the Bridge. Traffic Plying on the bridge from Aug-2009
                  
                   | 
               
            
              | 
                  
                  
                   | 
               
            
            
              | 
                Dated: 02 September 2009
                  
                   | 
               
            
              | 
                 Retaning Walls
                  
                   | 
               
            
              | 
                
                  
                  
                   | 
               
            
              | 
                 Constrcution of Retaining walls along the roadsite, as per design.
                  
                   | 
               
            
              | 
                  
                  
                   | 
               
            
            
              | 
                Dated: 02 September 2009
                  
                   | 
               
            
              | 
                 Retaining wall and Drain
                  
                   | 
               
            
              | 
                
                  
                  
                   | 
               
            
              | 
                 Drain and Retaining walls, work in Progress. 
                  
                   | 
               
            
              | 
                  
                  
                   | 
               
            
            |