ERA Projects
J&K ERA Main Logo
Govt. of Jammu and Kashmir
   
PROJECTS PAGE

Jammu & Kashmir Urban Sector Development Investment Program

Tranche-1 ADB Loan 2331-IND


 
SNo Sub Project Region Sector Scope Cost (INR crore) Award Date Completion Date Details
1 Approach Road Achhan Landfill Site Kashmir Urban SWM 0.443 Km 2.47 21 May 2008 12 October 2008 Link
2 Sanitary Landfill Cell-1 Kashmir Urban SWM 606 Kanals Single Site 23.58 26 November 2008 23 June 2011 Link
3 Sewerage Network PhaseII Lot-2 Jammu Urban Sewerage 80 KM 60.84 26 September 2009 30 November 2012 Link
4 Sewerage Network PhaseII Lot-1 Jammu Urban Sewerage 67 KM 24.44 26 September 2009 31 May 2012 Link
5 Sewerage Network PhaseII Lot-3 (JKGOV Project) Jammu Urban Sewerage 80 KM 52.87 06 October 2009 30 November 2012 Link
6 30 MLD Sewerage Treatment Plant at Jammu Jammu Urban Sewerage 30 MLD 29.35 08 April 2010 27 December 2012 Link
7 Raw Water DI Pipeline Harwan to Nishat Kashmir Urban Water Supply 5.1 KM 1000mm DI Pipe 15.05 21 October 2010 10 May 2012 Link
8 Sanitary Landfill Cell-2 Kashmir Urban SWM Cell-2 33.42 27 July 2012 Link
9 Sewerage Network PhaseII Lot-5 Jammu Urban Sewerage Pipe 30KM, Manholes:210, House Connection:210 10.83 27 June 2014 26 September 2016 Link
10 Sanitary Landfill Cell-3 Kashmir Urban SWM 122275MT (109mx72m) 430MT/Day 19.55 04 September 2015 04 October 2018 Link
11 Sewerage Network System in Ramzanpura (B) Jammu Urban Sewerage 14.09 10 February 2017 09 January 2018 Link
12 Sewerage Network System in Indira Vihar (A) Jammu Urban Sewerage 16.41 10 February 2017 10 January 2018 Link