SNo Sub Project Region Sector Scope Cost (INR crore) Award Date Completion Date Status
1 Bikram Chowk Flyover Project Jammu Transport Flyover 1.3KM Road Widening 8 lane 1.5KM 71.85 Works Completed
2 Storm Water Drainage at Channi-Himmat Jammu Jammu Urban Rehabilitation of drains - 8.263 Kms 15.16 Works Completed
3 Storm water drainage at Digiana and Gangyal (New) Jammu Urban Rehabilitation of drains - 20.313 Kms 98.44 Works Completed
4 Construction of Tube Wells in Jammu City Lot 1 Jammu Urban 19 Tube Wells 20.52 Works Completed
5 Replacement of Wornout Pipes and Const of 10 OHT,s in Jammu Jammu Urban 10 OHT + Replacement of Pipes 35.76 Works Allotted
6 Replacement of Wornout Machinery and Electrical equipment in Jammu Jammu Urban Replacement of machineries 23.92 Works Completed
7 NRW Study in Jammu Domestic Water Meter 20 DMA Jammu Urban NRW Study 4.60 Works Completed
8 Construction of Tube Wells in Jammu City Lot 2 Jammu Urban 7 nos. Tubewells 13.01 Works Completed
9 Solid Waste Management Equipment for SMC-Lot 2 Kashmir Urban Motorised Waste Collector (34) 2.37 Works Completed
10 Multilevel Parking facility at Srinagar Kashmir Transport 5 -level Automated Puzzle type parking 27.51 02 April 2013 30 April 2017 Works Completed
11 Jehangir Chowk to Rambagh Flyover Kashmir Transport 2.41 Km,4- Lane Flyover with 2 major bridges 341.26 07 May 2013 30 December 2017 Works Allotted
12 Storm Water Drainage Athwajan NH Bye pass Srinagar Kashmir Urban 9.445 KM Drainage Work 45.92 02 August 2013 29 August 2016 Works Allotted
13 Mobile Water Tankers, and OM Equipment for PHED Lot-4 Kashmir Urban One suction cum jetting machine 0.38 28 October 2013 28 May 2014 Works Completed
14 Solid Waste Management Equipment for SMC-Lot 4 Kashmir Urban Hook Loader 2 nos. and 10 nos. Containers 1.03 10 December 2013 10 June 2014 Works Completed
15 Solid Waste Management Equipment for SMC-Lot 1 Kashmir Urban 4 nos Rear End Loader Compactor with 300 nos. bins 1.90 14 June 2014 10 May 2015 Works Completed
16 Solid Waste Management Equipment for SMC-Lot 3 Kashmir Urban Dumper vehicle with Bins (10 Nos) 3.05 14 June 2014 14 August 2014 Works Completed
17 Solid Waste Management Equipment for SMC Rickshaw -Lot 5 Kashmir Urban 3.10 30 September 2014 30 November 2014 Works Completed
18 Mobile Water Tankers for PHED Lot-3 Kashmir Urban 2 Nos Pickup/delivery van 0.25 14 July 2015 14 March 2016 Works Completed
19 Mobile Water Tankers for PHED Lot-5 Kashmir Urban 0.38 16 July 2015 16 March 2016 Works Completed
20 Mobile Water Tankers for PHED Lot-1 Kashmir Urban 14 Nos Mobile Water Tankers 3.55 03 August 2015 03 August 2016 Works Allotted
21 Upgradation and Upliftment of existing drainage pumping stations in Srinagar LOT -A Kashmir Urban 14 nos of pumping stations 30.24 14 September 2015 31 December 2016 Works Allotted
22 Upgradation and Upliftment of existing drainage pumping stations in Srinagar LOT -B Kashmir Urban 9 nos. of pumping stations 19.11 14 September 2015 31 December 2016 Works Allotted
23 Equipment PHED Srinagar Lot1 Kashmir Urban 2.47 18 May 2016 18 August 2016 Works Completed
24 Equipment PHED Srinagar Lot4 Kashmir Urban 2.38 19 May 2016 19 August 2016 Works Completed
25 Equipment PHED Srinagar Lot2 Kashmir Urban 5.99 19 May 2016 19 August 2016 Works Completed
26 Equipment PHED Srinagar Lot3 Kashmir Urban 6.56 28 May 2016 28 August 2016 Works Completed
27 Equipment SMC Srinagar Lot8 Kashmir Transport 6.62 07 June 2016 07 August 2016 Works Completed
28 Equipment PHED Srinagar Lot7 Kashmir Urban 1.80 16 June 2016 16 September 2016 Works Completed
29 Equipment PHED Srinagar Lot5 Kashmir Urban 6.27 27 June 2016 27 October 2016 Works Completed
30 Equipment PHED Srinagar Lot6 Kashmir Urban 3.53 01 August 2016 15 September 2016 Works Completed
31 Equipment SMC Srinagar Lot9 Kashmir Urban 5.87 01 October 2016 01 January 2017 Works Completed
32 Equipment SMC Srinagar Lot11 Kashmir Urban 5.86 17 October 2016 17 January 2017 Works Completed
33 Equipment SMC Srinagar Lot10 Kashmir Urban 6.66 19 October 2016 19 January 2017 Works Completed