30 Tube Wells West Jammu Qty(10)(Lot 1)
10/10 Tube Wells West Jammu (Lot 1)

Loan:

2151-IND
Category: Engineers Design
Location: Jammu Urban Water Supply
Districts Passing:

Constituency Passing:

Status: Works Completed
ERA Ref: UJ/WS/2/01/NCB/07 (Lot-1) Type:Works Mode: LCB
ERA Pac ID: 0071.1
PCSS No: 0069
Scope of Work: 10 Nos
Contract Cost in Rs crore: 4.5548
Dynamic Cost in Rs crore: 6.56
Contractor Details Gurnam Singh and Co.
Date of Signing of Contract 04 January 2008
Date of Start of Work (NTP) 11 January 2008
Completion Period (15 Months)
Completion Date as per Contract 11 April 2009
 
All 10 nos. tube wells functional & handed over to PHE namely Science college I, II, III, Durga Nagar, PHE complex Barnai, Rajinder Nagar, Play Ground GMC, Dental College, Relief Commissioner Office & B.C.Road Kabir Colony






S. No.

Location

Discharge
Location

Rising Main to be connected /  proposed length in Mtrs.

1

Science College I
(Back side of  Hostel)

CPS Company Bagh

Interconnection & testing of rising work in progress

2

Science College II
 (left side of  Hostel)

CPS Company Bagh

Interconnection & testing of rising work in progress

3

Science College III
(left corner of main cricket ground)

CPS Company Bagh

Interconnection & testing of rising work in progress

4

Rajinder Nagar

OHT in vicinity

Interconnection to be done

5

Durga Nagar

Existing OHT in PHE Stn. near by 200m away

 

6

Dental College

Sump Tank

Survey of Rising main to be started.

7

Play Ground, Govt. Medical College

PHE Stn. Bakshi Ngr

Survey of Rising main to be started.

8

PHE Complex, Barnai

GLSR in complex

Interconnection required

9

Relief Commissioner Office

OHT GLSR (under construction) in the vicinity

Interconnection required

10

B.C. Road , Kabir Colony