| Balance work of Doodhganga nallah to Kralpora WTP |
| Balance work for Providing, Laying, Jointing, Testing and Commissioning of Raw water pipeline from higher reaches of Doodhganga nallah to Kralpora Water Treatment Plant at Srinagar” |
Loan:
|
3132-IND |
| Category: |
|
| Location: |
Kashmir Urban Water Supply |
| Districts Passing: |
|
Constituency Passing: |
|
| Status: |
Works Completed |
| ERA Ref: |
Type: Mode: |
| ERA Pac ID: |
550 |
| PCSS No: |
Temp-DoodG-2 |
| Scope of Work: |
|
| Contract Cost in Rs crore: |
3.97 |
| Dynamic Cost in Rs crore: |
3.97 |
| Contractor Details |
AIPL-ACC(JV) |
| Date of Signing of Contract |
|
| Date of Start of Work (NTP) |
27 May 2019 |
| Completion Period |
(0 Months) |
| Completion Date as per Contract |
|
|
|
| |
|
|
| |