ERA Projects
J&K ERA Main Logo
Govt. of Jammu and Kashmir
  Jehlum Tawi Flood Recovery Project (JTFRP) | Search | | Admin |
Project Details
GO BACK
Bijbehara Langanbal Road
Bijbehara Langanbal Road upto Aura Wildlife Sanctuary.
29 Km Road completed and handed over to R&B Div Khanabal

Loan:

2151-IND
Category: Engineers Design
Location: Kashmir Transport Roads
Districts Passing: Anantnag

Constituency Passing:

Status: Works Completed
ERA Ref: Transport/Srinagar/Road 15 Type:Works Mode: NCB
ERA Pac ID: 0028
PCSS No: 0056
Scope of Work: 29 Km
Contract Cost in Rs crore: 26.4483
Dynamic Cost in Rs crore: 41.77
Contractor Details RG Buildwell Ltd
DDR Approve Date 27 April 2007
DPR Approve Date
IFB Issue Date (Last) 26 June 2007
Technical BID Open Date 01 August 2007
Financial BID Open Date 03 September 2007
Letter of Acceptance to contractor (LOA) 22 October 2007
Date of Signing of Contract 05 November 2007
Date of Start of Work (NTP) 31 December 2007
Completion Period (27 Months)
Completion Date as per Contract 30 March 2010
 
Project Completed and handed over to R&B Department