Earthwork completed.
Breast wall - 8310 RM completed against 8288 RM.
Retaining wall - 6834 RM against 6806 RM.
Side drains - 30130 RM length completed out of 30355 RM.
Pipe Culverts- Completed.
GSB - Completed.
WMM - Completed.
DBM - 30.09 km completed out of 30.90.
SDBC- 26.02 Km completed out of 30.90.
Chokha nallah bridge: Completed except wearing course.
Road Chenani-Sudh Mahadev-Mantalai takes off from NH-1A in Udhampur District. National Highway 1A connects Pathankot with Srinagar via Jammu, Udhampur,Chenani, Patni-Top, Batote, Anantnag and Awantipora.