Chenani-Sudh Mahadev Road
Imptt/ UG of Chenani-Sudh Mahadev Road up to Mantalai. (completed on 31-may 2012 and handed over to PWD on 26-Sep-2012)
Chenani Sudh Mahadev Road

Loan:

2151-IND
Category: Design as you Built
Location: Jammu Transport Roads
Districts Passing:

Constituency Passing:

Status: Works Completed
ERA Ref: Type:Works Mode: LCB
ERA Pac ID: 0046
PCSS No: 0028B
Scope of Work: 30.90 KM
Contract Cost in Rs crore: 23.75
Dynamic Cost in Rs crore: 26.05
Contractor Details PBA Infrastructure
Date of Signing of Contract 18 December 2006
Date of Start of Work (NTP) 18 December 2006
Completion Period (24 Months)
Completion Date as per Contract 17 December 2008
 
Earthwork completed. Breast wall - 8310 RM completed against 8288 RM. Retaining wall - 6834 RM against 6806 RM. Side drains - 30130 RM length completed out of 30355 RM. Pipe Culverts- Completed.
GSB - Completed. WMM - Completed. DBM - 30.09 km completed out of 30.90. SDBC- 26.02 Km completed out of 30.90.
Chokha nallah bridge: Completed except wearing course.




Road Chenani-Sudh Mahadev-Mantalai takes off from NH-1A in Udhampur District. National Highway 1A connects Pathankot with Srinagar via Jammu, Udhampur,Chenani, Patni-Top, Batote, Anantnag and Awantipora.