Dachinpora Bridge
Construction of 2x25 mtr Bridge at Dachinpora
Dachinpora Bridge

Loan:

2151-IND
Category: Engineers Design
Location: Kashmir Transport Bridges
Districts Passing: Baramulla

Constituency Passing:

Rafiabad
Status: Works Completed
ERA Ref: Transport/Srinagar/Road 16 Type:Works Mode: LCB
ERA Pac ID: 0029
PCSS No: 0058
Scope of Work: 50 Mts
Contract Cost in Rs crore: 1.9571379
Dynamic Cost in Rs crore: 3.27
Contractor Details M.Shahnawaz Beigh
DDR Approve Date
DPR Approve Date
IFB Issue Date (Last) 14 July 2007
Technical BID Open Date 20 August 2007
Financial BID Open Date 13 September 2007
Letter of Acceptance to contractor (LOA) 05 November 2007
Date of Signing of Contract 21 November 2007
Date of Start of Work (NTP) 18 December 2007
Completion Period (15 Months)