Handwara Zachaldara Waddur Road
Handwara Zachaldara Waddur Road in district Kupwara
17 Km Road completed and handed over to R&B Deptt

Loan:

2151-IND
Category: Engineers Design
Location: Kashmir Transport Roads
Districts Passing: Kupwara

Constituency Passing:

Handwara
Status: Works Completed
ERA Ref: Transport/Srinagar/Road 14 Type:Works Mode: NCB
ERA Pac ID: 0027
PCSS No: 0080
Scope of Work: 17 Km
Contract Cost in Rs crore: 19.99
Dynamic Cost in Rs crore: 31.35
Contractor Details Rash Builders
DDR Approve Date
DPR Approve Date
IFB Issue Date (Last) 28 July 2007
Technical BID Open Date 10 September 2007
Financial BID Open Date 16 October 2007
Letter of Acceptance to contractor (LOA) 01 March 2008
Date of Signing of Contract 31 March 2008
Date of Start of Work (NTP) 10 May 2008
Completion Period (18 Months)
Completion Date as per Contract 08 November 2009