Handwara Zachaldara Waddur Road
Handwara Zachaldara Waddur Road in district Kupwara
17 Km Road completed and handed over to R&B Deptt

Loan:

2151-IND
Category: Engineers Design
Location: Kashmir Transport Roads
Districts Passing: Kupwara

Constituency Passing:

Handwara
Status: Works Completed
ERA Ref: Transport/Srinagar/Road 14 Type:Works Mode: NCB
ERA Pac ID: 0027
PCSS No: 0080
Scope of Work: 17 Km
Contract Cost in Rs crore: 19.99
Dynamic Cost in Rs crore: 31.35
Contractor Details Rash Builders
Date of Signing of Contract 31 March 2008
Date of Start of Work (NTP) 10 May 2008
Completion Period (18 Months)
Completion Date as per Contract 08 November 2009
 
Project Completed and handed over to (R&B) Deptt
Retaining Wall :- 2135 m completed out of 2135 m
Breast wall :- 1480 m completed out of 1480 m
Drain length :- 9715 m completed out of 9715 m
Pipe Culvert :-35 Nos Completed out of 46 no
Box Culvert :- 13 Nos Completed out of 15 no
Bridges :- 5 Nos Completed out of 5 no