Loan:
|
2151-IND |
Category: |
Design as you Built |
Location: |
Kashmir Transport Roads |
Districts Passing: |
|
Constituency Passing: |
|
Status: |
Works Completed |
ERA Ref: |
Transport/Srinagar/Road 03 Type:Works Mode: LCB |
ERA Pac ID: |
0002 |
PCSS No: |
0026 |
Scope of Work: |
37.6 Km |
Contract Cost in Rs crore: |
24.8763 |
Dynamic Cost in Rs crore: |
36.32 |
Contractor Details |
BLA Brahmaputra Consortium Ltd(JV) |
Date of Signing of Contract |
27 October 2006 |
Date of Start of Work (NTP) |
25 November 2006 |
Completion Period |
(24 Months) |
Completion Date as per Contract |
24 December 2008 |