Intake Boria Tanks Jammu East (Lot 1) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Design, Construction, Supply, Instalaltion, Testing, Commissioning, Trial Run, Operation & Maintenance of Civil, Mechanical, Electrical Equipment of Intake Pumping Station near Boria Jammu East (Lot 1) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Intake bohria completed by J&K ERA and commissioned on | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
All 16 nos river piles completed
All 10 nos. shore piles completed
Pipe : MS pipe 400mm dia laid 60m
Pump Room : Pump commissioned, concreting of roof slab done upto 321m level Beam: Concreting of beam at SP1, SP2, SP3, SP4, SP7 & SP8 completed upto 315m level. TB1 & TB6 concreting done at 310m level. Concreting of beams 5 nos. of DG room at 317.50m level completed. Concreting of 9 nos. beam of DG room / parking (half) completed. Concreting of 3 nos. beam at 310m level from pile cap to column completed, Reinforcement of 1 nos beam in progress Column: Concreting of column at SP1, SP2, SP3, SPC7, SPC8 completed upto 315m level. concreting at C3, C6, C2 & C5 done upto 317.4m level, concreting of C7 done upto 317.50m level. Reinforcement of column upto 320.30m level of DG room completed. concreting of 2 nos column from 310 to 314m level completed for parking area Bridge: Steel bridge completed, concreting of walkway slab completed at 315m level. Slab: Concreting of roof slab of DG room & half parking floor slab completed at 320.30m level Brick Work: DG room, Parking & pump room in progress Bracing between river pile: Bracing work at 303m, 306m level completed, 300m 309m & 315m level is in progress, Grating for pump protection in progress. Concreting of retaining wall (half portion) completed. Bridge: Steel bridge completed, concreting of walkway slab completed at 315m level. Slab: Concreting of roof slab of DG room & half parking floor slab completed at 320.30m level Brick Work: DG room completed, Parking, office room & pump room in progress Bracing between river pile: Bracing work at 303m, 306m, 309m level completed, 309m & 315m level is in progress, Grating for pump protection in progress. Concreting of retaining wall (half portion) completed Finishing work: Plastering below floor slab, DG room & Walkway bridge completed, roof slab of DG room and pump house in progress |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||