Kaghote Nallah Bridge
Construction of 41m span Steel Girder Bridge over Kaghote Nallah on Udhampur /Ramnagar road (completed on 31-5-2012).

Loan:

2151-IND
Category: Forced Account
Location: Jammu Transport Bridges
Districts Passing:

Constituency Passing:

Status: Works Completed
ERA Ref: Type:Works Mode: Force Account
ERA Pac ID: 0053
PCSS No: 0022
Scope of Work: 47 Mt
Contract Cost in Rs crore: 1.99
Dynamic Cost in Rs crore: 3.63
Contractor Details JKPCC
DDR Approve Date
DPR Approve Date
IFB Issue Date (Last)
Technical BID Open Date
Financial BID Open Date
Letter of Acceptance to contractor (LOA) 16 February 2006
Date of Signing of Contract 28 February 2006
Date of Start of Work (NTP) 28 February 2006
Completion Period (25 Months)
Completion Date as per Contract 29 March 2008