Kali Bari Kathua-Hatli Morh Road
Kali Bari Kathua- Hatli Morh Road
Kali Bari Kathua-Hatli Morh Road

Loan:

2151-IND
Category: Engineers Design
Location: Jammu Transport Roads
Districts Passing:

Constituency Passing:

Status: Works Completed
ERA Ref: Type:Works Mode: NCB
ERA Pac ID: 0064
PCSS No: 0085
Scope of Work: 6.57 KM
Contract Cost in Rs crore: 22.61
Dynamic Cost in Rs crore: 22.61
Contractor Details Khajuria Construction JV
Date of Signing of Contract 09 April 2008
Date of Start of Work (NTP) 07 May 2008
Completion Period (24 Months)
Completion Date as per Contract 07 May 2010
 
Earthwork - 5.827 km completed in stretches. Side Drain - 8963 RM length completed out of 11000 RM. GSB - 3.6 km (RHS) completed out of 6.470 km & 4.818 km (LHS) completed out of 6.470.
WMM (Ist Layer) - 3.425 km (RHS) completed out of 6.470 km WMM (Ist Layer) - 4.451 km (LHS) completed out of 6.470 km WMM (2nd Layer) - 2.630 km (RHS) completed out of 6.470 km WMM (2nd Layer) - 2.800 km (LHS) completed out of 6.470 km
BM - 2.630 km (RHS) competed out of 6.470 km and 2.800 km (LHS) completed out of 6.470 Median Kerb - 1.50 km completed out of 6.00 km. Major Bridge: Finishing work is in progress. Canal Bridge No.1:Completed Canal Bridge No. 2: Completed.