Kooh Nallah Bridge
Construction of 42m span Steel Girder Bridge over Kooh Nallah on Udhampur Ramnagar road .*
Slow progress recorded on 10-March-2008, a bridge under execution by JKPCC.

Loan:

2151-IND
Category: Forced Account
Location: Jammu Transport Bridges
Districts Passing:

Constituency Passing:

Status: Works Completed
ERA Ref: Type:Works Mode: Force Account
ERA Pac ID: 0052
PCSS No: 0023
Scope of Work: 45 Mt
Contract Cost in Rs crore: 2.08
Dynamic Cost in Rs crore: 4.01
Contractor Details JKPCC
DDR Approve Date
DPR Approve Date
IFB Issue Date (Last)
Technical BID Open Date
Financial BID Open Date
Letter of Acceptance to contractor (LOA) 16 February 2006
Date of Signing of Contract 28 February 2006
Date of Start of Work (NTP) 28 February 2006
Completion Period (25 Months)
Completion Date as per Contract 31 March 2008
 
The total span of the bridge is 45m.The Bridge is located in district udhampur.The contract was awarded to JKPCC under force account for an amount of Rs1.83cr.On 20-02-2006.Due to site condition the design was changed & supplementary agreement was drawn.