Landoichoi Primary Drain
Rehabilitation and Chanelization of Landoichai primary drain

Loan:

2151-IND
Category: Engineering Design
Location: Jammu Urban Drainage
Districts Passing:

Constituency Passing:

Status: Works Completed
ERA Ref: UJ/SWD/Part of 10/02/LCB/06 Type:Works Mode: LCB
ERA Pac ID: 0059
PCSS No: 0033
Scope of Work: 6 Km
Contract Cost in Rs crore: 17.3932026
Dynamic Cost in Rs crore: 23.31
Contractor Details Laxmi Narayan Agarwal
DDR Approve Date
DPR Approve Date
IFB Issue Date (Last) 17 October 2006
Technical BID Open Date 20 November 2006
Financial BID Open Date 29 December 2006
Letter of Acceptance to contractor (LOA) 24 January 2007
Date of Signing of Contract 02 March 2007
Date of Start of Work (NTP) 08 March 2007
Completion Period (18 Months)
Completion Date as per Contract 07 September 2008
 
Scope length of the nallahs: 5.85Km. Population served 130844 Total area to be served -- 20.2 Sq Km. Areas to be benefited are --- Transport Nagar, Narwal, Nanak Nagar, Shastri Nagar, Channi area, Satwari, Jeewan Nagar, Sanjay Nagar etc.