Lethpora-Penthachowk Road
Lethpora-Penthachowk loop including Lethpora ladoo-Pampore Khrew road(Pulwama & Srinagar Districts)
38.5 Km road Completed and handed over to R&B Deptt

Loan:

2151-IND
Category: Design as you Built
Location: Kashmir Transport Roads
Districts Passing: Pulwama/Srinagar

Constituency Passing:

Status: Works Completed
ERA Ref: Transport/Srinagar/Road 04 Type:Works Mode: LCB
ERA Pac ID: 0006
PCSS No: 0025
Scope of Work: 38.5 Km
Contract Cost in Rs crore: 25.0007
Dynamic Cost in Rs crore: 34.81
Contractor Details BLA-MK (JV)
DDR Approve Date
DPR Approve Date
IFB Issue Date (Last) 20 December 2005
Technical BID Open Date 15 February 2006
Financial BID Open Date 13 June 2006
Letter of Acceptance to contractor (LOA) 27 July 2006
Date of Signing of Contract 13 October 2006
Date of Start of Work (NTP) 11 November 2006
Completion Period (24 Months)
Completion Date as per Contract 23 November 2008
 
1.Lethpora-Ladhoo 5.1 Km
2.Pampore-Ladhoo 8.8 Km
3.Ladhoo-Khrew-Wuyan 6.7 Km
4. Wuayan- Sampora 6.9 Km
5.Wuyan-Panthachowk 10.8 Km