Missing Links Pohru Chowk-Noora Hospital (Zone-1)
Construction of Drainage Network Missing Links Zone-1st from Pohru Chowk to Noora Hospital (left Side of left bank of River Jehlum)
Construction of Manhole

Loan:

JTFRP
Category:
Location: Kashmir Urban Drainage
Districts Passing:

Constituency Passing:

Status: Works Allotted
ERA Ref: Type: Mode:
ERA Pac ID: JTFRP-K03
PCSS No: JTFRP-K03
Scope of Work: 40.26 Km
Contract Cost in Rs crore: 54.7
Dynamic Cost in Rs crore: 54.70
Contractor Details HRCC Pvt Ltd
Date of Signing of Contract
Date of Start of Work (NTP) 01 June 2020
Completion Period (18 Months)
Completion Date as per Contract 25 December 2021
 
Work in Progress
9700 Mtrs Completed