Project Details
GO BACK
Natipora-Nowgam and Newa-Pulwama Road
Natipora-Nowgam and Newa-Pulwama- Road (Budgam Pulwama)two roads combined
23.79 Km road completed and handed ovet to R&B Deptt

Loan:

2151-IND
Category: Engineers Design
Location: Kashmir Transport Roads
Districts Passing: Budgam/Srinagar/Pulwama

Constituency Passing:

Status: Works Completed
ERA Ref: Transport/Srinagar/Road/08 Type:Works Mode: LCB
ERA Pac ID: 0008
PCSS No: 0039
Scope of Work: 23.79 Km
Contract Cost in Rs crore: 23.99
Dynamic Cost in Rs crore: 27.27
Contractor Details BJCL
DDR Approve Date 21 August 2006
DPR Approve Date
IFB Issue Date (Last) 19 December 2006
Technical BID Open Date 03 February 2007
Financial BID Open Date 22 February 2007
Letter of Acceptance to contractor (LOA) 23 March 2007
Date of Signing of Contract 15 May 2007
Date of Start of Work (NTP) 13 June 2007
Completion Period (24 Months)
Completion Date as per Contract 10 July 2009