GO
BACK |
Nowgam-Bonpora-Padshahi Bagh Drainage Scheme |
Construction of Nowgam-Bonpora-Padshahi Bagh Drainage Scheme |
|
Concrete Manhole |
Loan:
|
JTFRP |
Category: |
Engineers Design |
Location: |
Kashmir Urban Drainage |
Districts Passing: |
|
Constituency Passing: |
|
Status: |
Works Allotted |
ERA Ref: |
Type: Mode: |
ERA Pac ID: |
JTFRP-K02 |
PCSS No: |
JTFRP-K02 |
Scope of Work: |
12 Km |
Contract Cost in Rs crore: |
28.74 |
Dynamic Cost in Rs crore: |
28.74 |
Contractor Details |
Wani Infratech Pvt Ltd |
Date of Signing of Contract |
01 June 2020 |
Date of Start of Work (NTP) |
01 June 2020 |
Completion Period |
(18 Months) |
Completion Date as per Contract |
22 December 2021 |
|
|
|
Work in progress
4400 mtrs completed
|
Population Benefit: 33000 souls
Areas Benefited 120.88 hectares |
|