| OverHead Tanks Jammu East (Lot 2) |
| OverHead Tanks Jammu East (Lot 2) Shastri Nagar, Gandhi Nagar, Channi Himat, Trikutanagar and Rail Head Complex |
Loan:
|
2151-IND |
| Category: |
Design as you Built |
| Location: |
Jammu Urban Water Supply |
| Districts Passing: |
|
Constituency Passing: |
|
| Status: |
Works Completed |
| ERA Ref: |
Type:Supply of Goods Mode: LCB |
| ERA Pac ID: |
0068.2 |
| PCSS No: |
0061 |
| Scope of Work: |
9 OHT 4 GLSR |
| Contract Cost in Rs crore: |
11.8756 |
| Dynamic Cost in Rs crore: |
12.34 |
| Contractor Details |
Prabhu Dayal Kanojia |
| Date of Signing of Contract |
10 December 2007 |
| Date of Start of Work (NTP) |
24 December 2007 |
| Completion Period |
(18 Months) |
| Completion Date as per Contract |
23 June 2009 |
|
|
| |
9 Nos OHT's Comissioned Namely: Rail Head, D/C Block Balmiki Nagar, T/W -9 PHE Sub division, Shastri Nagar, T/W -1, PHE Complex Trikuta Nagar, Nanak Nagar Sec -7, PHE Complex Channi himmat & Ravi Gas Agency Gandhi Nagar
4 Nos GLSR's Commissioned Namely: PHE Complex Narwal, Tube Well No.1, Boria Pumping Station, Old Channi
|
S
|
S.No.
|
Location
|
|
|
|
OHT
|
|
|
1
|
Shastri
Nagar PHE Division - 1.5 Lac Gallon
|
|
|
|
2
|
Tube Well No. 9 PHE Sub Division - 1.5 Lac Gallon
|
|
|
|
3
|
PHE Complex, Channi
Himmat - 3.0 Lac Gallon
|
|
|
|
4
|
Tube Well No. 1 PHE Sub Division - 1.5 Lac Gallon
|
|
|
|
5
|
Rail Head - 1.5 Lac Gallon
|
|
|
|
6
|
PHE Complex, Trikuta
Nagar - 3.0 Lac Gallon
|
|
|
|
7
|
Gandhi Nagar, Extn-II
- 3.0 Lac Gallon
|
|
|
|
8
|
D/C Block Balmiki
Nagar - 1.5 Lac Gallon
|
|
|
|
9
|
Nanak Nagar, Sec - 7 - 1.5 Lac
Gallon
|
|
|
|
GLSR
|
|
|
1
|
PHE Complex, Trikuta
Nagar - 3.0 Lac Gallon
|
|
|
|
2
|
Boria
Pumping Station - 3.0 Lac Gallon
|
|
|
|
3
|
PHE, Complex, Narwal
- 3.0 Lac Gallon
|
|
|
|
4
|
Tube Well No.1 - 1.0 Lac Gallon
|
|
|
|
| |