Bridge at Padshahi Bagh allotted to JKPCC,Cancelled and Retendered on 1-April-2009 Reallotted on 30-Sep-2009 earlier JKPCC Cost:1.66 Crores OLD PCSS:0040

Loan:

2151-IND
Category: Engineers Design
Location: Kashmir Transport Bridges
Districts Passing:

Constituency Passing:

Status: Contracts Terminated
ERA Ref: Transport Srinagar/Roads/44 Type:Works Mode: LCB
ERA Pac ID: 0075
PCSS No: 0104
Scope of Work: 26Mts
Contract Cost in Rs crore: 2.18
Dynamic Cost in Rs crore: 2.42
Contractor Details Riaz Construction
DDR Approve Date
DPR Approve Date
IFB Issue Date (Last) 01 April 2009
Technical BID Open Date 11 May 2009
Financial BID Open Date
Letter of Acceptance to contractor (LOA) 11 August 2009
Date of Signing of Contract 24 August 2009
Date of Start of Work (NTP) 21 September 2009
Completion Period (12 Months)
Completion Date as per Contract 20 September 2010