Potkhah-Pachar Road
Widenening and Strengthening of Potkhah to Pachar Road
Details later

Loan:

2151-IND
Category: Design as you Built
Location: Kashmir Transport Roads
Districts Passing: Baramulla

Constituency Passing:

Sangrama/Baramulla
Status: Works Completed
ERA Ref: Transport Srinagar/Roads/05 Type:Works Mode: LCB
ERA Pac ID: 0005
PCSS No: 0031
Scope of Work: 15.74 Km
Contract Cost in Rs crore: 9.173
Dynamic Cost in Rs crore: 15.65
Contractor Details Dinesh Chandra Const Company
Date of Signing of Contract 26 December 2006
Date of Start of Work (NTP) 31 January 2007
Completion Period (18 Months)
Completion Date as per Contract 21 August 2008
 
Retaining Wall :- 4050 m completed out of 4050 m
Breast wall :- 1100 m completed out of 1100 m
Drain length :- 1800 m completed out of 1800 m
Pipe Culvert :- 38 Nos Completed out of 38 no
Box Culvert :- 4 Nos Completed out of 4 no
Bridges :- 1 Nos Completed out of 1 no