Raw Water DI Pipeline Harwan to Nishat
Procurement Works of "Providing, Laying, Joining,Testing and Commissioning of Raw Water Transmission Main from Harwan Reservoir to Nishat Water Treatment Plant in Srinagar City".

Loan:

2331-IND
Category: Engineers Design
Location: Kashmir Urban Water Supply
Districts Passing:

Constituency Passing:

Status: Works Completed
ERA Ref: JKUSDIP Srinagar/WS-01 Type:Works Mode: NCB
ERA Pac ID: 201
PCSS No: 0009-02
Scope of Work: 5.1 KM 1000mm DI Pipe
Contract Cost in Rs crore: 16.57672
Dynamic Cost in Rs crore: 15.05
Contractor Details Vishwa Infrstructure & Service
DDR Approve Date
DPR Approve Date
IFB Issue Date (Last) 17 April 2010
Technical BID Open Date 18 June 2010
Financial BID Open Date 10 August 2010
Letter of Acceptance to contractor (LOA) 06 September 2010
Date of Signing of Contract 21 October 2010
Date of Start of Work (NTP) 11 November 2010
Completion Period (18 Months)
Completion Date as per Contract 10 May 2012