Rawalpora-Tengpora Drain
Construction of trunk drain, main drain, sub-mains along N.H. Bypass road including construction of pump house and other allied civil works Rawalpora chowk to Tengpora Bridge (Scope Revised from 24.97 Km to 24.84)
Interior view of pumping station of Rawalpora Tengpora Drainage Scheme

Loan:

2151-IND
Category: Engineers Design
Location: Kashmir Urban Drainage
Districts Passing:

Constituency Passing:

Status: Works Completed
ERA Ref: JK/US/SWD/17/02/NCB/06 Type:Works Mode: LCB
ERA Pac ID: 0025
PCSS No: 0050
Scope of Work: 24.84 KM
Contract Cost in Rs crore: 32.8961
Dynamic Cost in Rs crore: 73.56
Contractor Details Hassan Const Company
Date of Signing of Contract 10 August 2007
Date of Start of Work (NTP) 23 August 2007
Completion Period (18 Months)
Completion Date as per Contract 22 February 2009
 
Partially Commissioned (Inaugurated by Hon’ble Chief Minister, J&K State on 14th November, 2012)
Trunk Drain: 3.265 Km Completed out of 3.265 Km
Main Drain: 1.625 Km Completed out of 1.625 Km




Sub Project completed with revised scope and handed over to SMC