ERA Projects
J&K ERA Main Logo
Govt. of Jammu and Kashmir
   
PROJECTS PAGE
GO BACK
Replacement of Worn out Pipes Distribution System (Phase I)
Replacement of worn-out pipes and Strengthening of Distribution Network in Jammu city , Phase I

Loan:

2151-IND
Category: Engineers Design
Location: Jammu Urban Water Supply
Districts Passing:

Constituency Passing:

Status: Works Allotted
ERA Ref: UJ/WS/04/01/NCB/07 Type:Works Mode: NCB
ERA Pac ID: 0066
PCSS No: 0075
Scope of Work: 86 Km
Contract Cost in Rs crore: 29.5321948
Dynamic Cost in Rs crore: 33.80
Contractor Details Modern Construction Company
Date of Signing of Contract 15 February 2008
Date of Start of Work (NTP) 22 February 2008
Completion Period (18 Months)
Completion Date as per Contract 21 August 2009
 
Scope-86 Km Pipe Line Laid - 82.70 Kms. Pipe Line tested - 56.49 Kms Pipe Line Commissioned - 34.23 Kms. Road restoration (WBM)- 50.22 Kms Location: Gandhi Nagar,Chand Nagar, Shastri Nagar
Road restoration (WBM)- 50.22 Kms Location: Gandhi Nagar,Chand Nagar, Shastri Nagar





Sr

Sr. No.

Site

1

Gandhi Nagar area

2

Shastri Nagar area

3

Old City area

4

Nanak Nagar area

5

Deep Nagar area

6

Ambica Colony area

7

Nakrain to Panama Chowk