Loan:
|
2151-IND |
Category: |
Forced Account |
Location: |
Kashmir Transport Bridges |
Districts Passing: |
|
Constituency Passing: |
|
Status: |
Works Completed |
ERA Ref: |
Transport Srinagar/Bridge/06 Type:Works Mode: LCB |
ERA Pac ID: |
0019 |
PCSS No: |
0041 |
Scope of Work: |
22Mts |
Contract Cost in Rs crore: |
1.08 |
Dynamic Cost in Rs crore: |
1.08 |
Contractor Details |
JKPCC |
Date of Signing of Contract |
14 June 2007 |
Date of Start of Work (NTP) |
14 June 2007 |
Completion Period |
(24 Months) |
Completion Date as per Contract |
13 June 2009 |