Loan:
|
2151-IND |
| Category: |
Forced Account |
| Location: |
Kashmir Transport Bridges |
| Districts Passing: |
|
Constituency Passing: |
|
| Status: |
Works Completed |
| ERA Ref: |
Transport Srinagar/Bridge/06 Type:Works Mode: LCB |
| ERA Pac ID: |
0019 |
| PCSS No: |
0041 |
| Scope of Work: |
22Mts |
| Contract Cost in Rs crore: |
1.08 |
| Dynamic Cost in Rs crore: |
1.08 |
| Contractor Details |
JKPCC |
| Date of Signing of Contract |
14 June 2007 |
| Date of Start of Work (NTP) |
14 June 2007 |
| Completion Period |
(24 Months) |
| Completion Date as per Contract |
13 June 2009 |