Loan:
|
JTFRP |
| Category: |
|
| Location: |
Kashmir Transport Roads |
| Districts Passing: |
|
Constituency Passing: |
|
| Status: |
Works Allotted |
| ERA Ref: |
Type: Mode: |
| ERA Pac ID: |
JTFRP-K15 |
| PCSS No: |
JTFRP-K15 |
| Scope of Work: |
4.793 Km |
| Contract Cost in Rs crore: |
6.76 |
| Dynamic Cost in Rs crore: |
6.76 |
| Contractor Details |
Mirz Infrastructure |
| Date of Signing of Contract |
|
| Date of Start of Work (NTP) |
26 September 2020 |
| Completion Period |
(12 Months) |
| Completion Date as per Contract |
24 March 2022 |