Sangrama-Sopore-Kulangam Road
Sangrama- Sopore-Kulangam road (Baramulla Kupwara)
27.3 Km road completed and handed over to R&B Deptt

Loan:

2151-IND
Category: Design as you Built
Location: Kashmir Transport Roads
Districts Passing: Baramulla/Kupwara

Constituency Passing:

Sangrama/Sopore/Handwara
Status: Works Completed
ERA Ref: Transport/Srinagar/Road 02 Type:Works Mode: LCB
ERA Pac ID: 0003
PCSS No: 0024
Scope of Work: 27.3 Km
Contract Cost in Rs crore: 25.5041
Dynamic Cost in Rs crore: 38.32
Contractor Details ABCI(JV)
Date of Signing of Contract 26 October 2006
Date of Start of Work (NTP) 05 December 2006
Completion Period (24 Months)
Completion Date as per Contract 21 December 2008
 
Project completed and handed over to R&B Deptt






SANGRAMA –SOPORE- KULANGAM ROAD SUBPROJECT:

PROJECT SUMMARY:

Sangrama-SoporeKulangam road subproject of 27.3 Km involves an estimated cost of 33.19 crore . The road takes off from Km 43RD of Srinagar Baramulla National Highway 1A(NH-1A) and ends at Km 83RD of BaramullaKupwara road at Kulangam.

The road is of great significance as it passes through Sopore town popularly known as Apple town -an important business hub. The augmentation of the dilapidated road will give further push to economic activity besides, providing facilities to masses in communication sector.