Sanitary Landfill Cell-2
Construction of sencond cell at Sanitary Landfill Cell at Sringar

Loan:

2331-IND
Category: Engineers Design
Location: Kashmir Urban SWM
Districts Passing:

Constituency Passing:

Status: Works Completed
ERA Ref: Type:Works Mode: NCB
ERA Pac ID: 22
PCSS No: 0012-02
Scope of Work: Cell-2
Contract Cost in Rs crore: 18.6125
Dynamic Cost in Rs crore: 33.42
Contractor Details Khilari Infrastructures
Date of Signing of Contract 27 July 2012
Date of Start of Work (NTP) 10 September 2012
Completion Period (39 Months)
Completion Date as per Contract
 
Project completed and handed over to SMC