Sanitary Landfill Cell-3
Sanitary Landfill Cell-3

Loan:

2331-IND
Category: Engineers Design
Location: Kashmir Urban SWM
Districts Passing:

Constituency Passing:

Status: Works Completed
ERA Ref: Type:Works Mode: NCB
ERA Pac ID: 345cell2
PCSS No: 0014-01
Scope of Work: 122275MT (109mx72m) 430MT/Day
Contract Cost in Rs crore: 19.5463
Dynamic Cost in Rs crore: 19.55
Contractor Details Khilari Infrastructures
Date of Signing of Contract 04 September 2015
Date of Start of Work (NTP) 12 September 2015
Completion Period (37 Months)
Completion Date as per Contract 04 October 2018
 
Project completed and handed over to SMC