Sewerage Network PhaseII Lot-3 (JKGOV Project)
Providing, Laying, Jointing, Testing and Commissioning of Sewerage Network in Bhawani-Nagar area of Division A PhaseII at Jammu

Loan:

2331-IND
Category: Engineers Design
Location: Jammu Urban Sewerage
Districts Passing:

Constituency Passing:

Status: Contracts Terminated
ERA Ref: JKUSDIP Jammu/WW/03 Type:Works Mode: NCB
ERA Pac ID: 0203.3
PCSS No: JKGov-02
Scope of Work: 80 KM
Contract Cost in Rs crore: 47.2465045
Dynamic Cost in Rs crore: 52.87
Contractor Details Trans Tech Turnkey Pvt. Ltd
DDR Approve Date
DPR Approve Date
IFB Issue Date (Last) 02 March 2009
Technical BID Open Date 03 August 2009
Financial BID Open Date 22 August 2009
Letter of Acceptance to contractor (LOA) 30 September 2009
Date of Signing of Contract 06 October 2009
Date of Start of Work (NTP) 01 December 2009
Completion Period (36 Months)
Completion Date as per Contract 30 November 2012