Shahdara-KamalKote Road
Improvement and Upgradation of Shahdara-Kamalkote road starting from Dachi and completing at KamalKot passing through Sultan Daki
Shahdara Kamalkote Road (Scope 12.5 Km)

Loan:

2151-IND
Category: Engineers Design
Location: Kashmir Transport Roads
Districts Passing: Baramulla

Constituency Passing:

Uri
Status: Works Completed
ERA Ref: Transport/Srinagar/Roads/29 Type:Works Mode: NCB
ERA Pac ID: 0039
PCSS No: 0101
Scope of Work: 12.50 Km
Contract Cost in Rs crore: 19.0676
Dynamic Cost in Rs crore: 21.71
Contractor Details Rash Builders
DDR Approve Date
DPR Approve Date
IFB Issue Date (Last) 13 November 2007
Technical BID Open Date
Financial BID Open Date
Letter of Acceptance to contractor (LOA) 01 April 2009
Date of Signing of Contract 01 May 2009
Date of Start of Work (NTP) 05 May 2009
Completion Period (24 Months)
Completion Date as per Contract 04 May 2011