Singhpora Kanihama Road
Singhpora Kanihama Gundkhaja Qasim Road

Loan:

2151-IND
Category: Engineers Design
Location: Kashmir Transport Roads
Districts Passing: Baramulla

Constituency Passing:

Status: Works Completed
ERA Ref: Transport/Srinagar/Road 13 Type:Works Mode: LCB
ERA Pac ID: 0011
PCSS No: 0049
Scope of Work: 6.70 Km
Contract Cost in Rs crore: 5.7797413
Dynamic Cost in Rs crore: 7.80
Contractor Details Gousia Road Construction
DDR Approve Date 31 January 2007
DPR Approve Date
IFB Issue Date (Last) 16 April 2007
Technical BID Open Date 21 May 2007
Financial BID Open Date 22 June 2007
Letter of Acceptance to contractor (LOA) 31 July 2007
Date of Signing of Contract 20 August 2007
Date of Start of Work (NTP) 21 September 2007
Completion Period (18 Months)
Completion Date as per Contract 15 April 2009