Sonwani Bridge
Construction of 3 X30 Mtr span bridge over pohru Nallah at Sonwani.(Major)
3x30 Mtr Span Bridge completed and handed over to R&B division Handwara

Loan:

2151-IND
Category: Engineers Design
Location: Kashmir Transport Bridges
Districts Passing: Kupwara/Baramulla

Constituency Passing:

Langate/Sopore
Status: Works Completed
ERA Ref: Transport/Srinagar/Road/19 Type:Works Mode: LCB
ERA Pac ID: 0031
PCSS No: 0065
Scope of Work: 3x30 Mts Span
Contract Cost in Rs crore: 4.98
Dynamic Cost in Rs crore: 5.32
Contractor Details New Asia Const Company
Date of Signing of Contract 18 December 2007
Date of Start of Work (NTP) 23 January 2008
Completion Period (15 Months)
Completion Date as per Contract 05 May 2009
 
Project Completed and handed over to R&B Department