ERA Projects
J&K ERA Main Logo
Govt. of Jammu and Kashmir
   
PROJECTS PAGE
GO BACK
Strengthening of Existing System Rising Mains (Phase-I)
Replacement of Rising mains, laying new rising mains & gravity mains in various parts of Jammu city [Strengthening of existing system (Phase-I)

Loan:

2151-IND
Category: Engineers Design
Location: Jammu Urban Water Supply
Districts Passing:

Constituency Passing:

Status: Works Completed
ERA Ref: Type:Works Mode: LCB
ERA Pac ID: 0054
PCSS No: 0019
Scope of Work: 600-100 dia 60 km
Contract Cost in Rs crore: 23.25
Dynamic Cost in Rs crore: 24.36
Contractor Details Electrosteel Casting Ltd
Date of Signing of Contract 14 September 2006
Date of Start of Work (NTP) 29 September 2006
Completion Period (18 Months)
Completion Date as per Contract 28 March 2008
 
57.26 Km pipe laid. Hydrostatic Test for 57.26 Km completed.
Contract fore closed





Length of Pipe line: - 60 Kms.Total area to be served: - 40 Sq. Km.Population served : - 3,00,000 souls Areas benefitted : - Karyani, Thangar,Bhitindi,Sainik Colony,Prade,Greater Kailash,Nowabadetcin Jammu east & Prade,Roop Nagar, Bakshi Nagar, Rajpura etc in Jammu West and also conveying water from the proposed tube wells to scarcity areas.