ERA Projects
J&K ERA Main Logo
Govt. of Jammu and Kashmir
  Jehlum Tawi Flood Recovery Project (JTFRP) | Search | | Admin |
Project Details
GO BACK
Tokina Bridge
Tokina Bridge
Tokina Bridge as on 23 September 2013

Loan:

2151-IND
Category: Engineers Design
Location: Kashmir Transport Bridges
Districts Passing:

Constituency Passing:

Status: Works Completed
ERA Ref: Transport/Srinagar/Bridge 30 Type:Works Mode: LCB
ERA Pac ID: 0043
PCSS No: 0086
Scope of Work: 4x30 Mts
Contract Cost in Rs crore: 9.06
Dynamic Cost in Rs crore: 13.11
Contractor Details Tarmac Builders
DDR Approve Date
DPR Approve Date
IFB Issue Date (Last) 15 December 2007
Technical BID Open Date 23 January 2008
Financial BID Open Date 17 March 2008
Letter of Acceptance to contractor (LOA) 02 May 2008
Date of Signing of Contract 29 May 2008
Date of Start of Work (NTP) 09 August 2008
Completion Period (18 Months)
Completion Date as per Contract 28 November 2009