Tokina Bridge
Tokina Bridge
Tokina Bridge as on 23 September 2013

Loan:

2151-IND
Category: Engineers Design
Location: Kashmir Transport Bridges
Districts Passing:

Constituency Passing:

Status: Works Completed
ERA Ref: Transport/Srinagar/Bridge 30 Type:Works Mode: LCB
ERA Pac ID: 0043
PCSS No: 0086
Scope of Work: 4x30 Mts
Contract Cost in Rs crore: 9.06
Dynamic Cost in Rs crore: 13.11
Contractor Details Tarmac Builders
Date of Signing of Contract 29 May 2008
Date of Start of Work (NTP) 09 August 2008
Completion Period (18 Months)
Completion Date as per Contract 28 November 2009
 
Project completed and Handed over to R&B Department