ERA Projects
J&K ERA Main Logo
Govt. of Jammu and Kashmir
  Jehlum Tawi Flood Recovery Project (JTFRP) | Search | | Admin |
Project Details
GO BACK
Town Roads Kargil - Lot2 (G.M Pora,Trespone link roads )
Strengthening upto WBM Level of G.M Pora & Trespone link roads at Kargil

Loan:

2151-IND
Category: Engineers Design
Location: Kashmir Transport Roads
Districts Passing:

Constituency Passing:

Status: Works Completed
ERA Ref: Type:Works Mode: LCB
ERA Pac ID: 0072.2
PCSS No: 0083
Scope of Work: 5.70 KM
Contract Cost in Rs crore: 1.49
Dynamic Cost in Rs crore: 3.68
Contractor Details Mohammad Ali
DDR Approve Date
DPR Approve Date
IFB Issue Date (Last) 24 September 2007
Technical BID Open Date 01 November 2007
Financial BID Open Date 12 January 2008
Letter of Acceptance to contractor (LOA) 05 April 2008
Date of Signing of Contract 24 April 2008
Date of Start of Work (NTP) 30 May 2008
Completion Period (9 Months)
Completion Date as per Contract 28 February 2009