Town Roads Leh G3-Lot-01 (Urbis Bridge)
Urbis Bridge in Leh (Contract terminated on 18-1-2013) Scope= 55 m Revised =71.45 m

Loan:

2151-IND
Category: Engineers Design
Location: Kashmir Transport Bridges
Districts Passing:

Constituency Passing:

Status: Contracts Terminated
ERA Ref: Type:Works Mode: LCB
ERA Pac ID: 0073.6
PCSS No: 0095
Scope of Work: 71045 Mtr Span
Contract Cost in Rs crore: 3.03
Dynamic Cost in Rs crore: 3.57
Contractor Details Granco Industries
DDR Approve Date
DPR Approve Date
IFB Issue Date (Last) 12 February 2008
Technical BID Open Date 10 April 2008
Financial BID Open Date 26 May 2008
Letter of Acceptance to contractor (LOA) 05 September 2008
Date of Signing of Contract 04 December 2008
Date of Start of Work (NTP) 02 January 2009
Completion Period (12 Months)
Completion Date as per Contract 31 December 2009
 
Contract terminated on 18-01-2013 due to non-performance of the contractor and handed over to JKPCC for execution of Balance work