Town Roads Kargil - Lot2 (G.M Pora,Trespone link roads ) |
Strengthening upto WBM Level of G.M Pora & Trespone link roads at Kargil |
Loan:
|
2151-IND |
Category: |
Engineers Design |
Location: |
Kashmir Transport Roads |
Districts Passing: |
|
Constituency Passing: |
|
Status: |
Works Completed |
ERA Ref: |
Type:Works Mode: LCB |
ERA Pac ID: |
0072.2 |
PCSS No: |
0083 |
Scope of Work: |
6.53 KM |
Contract Cost in Rs crore: |
1.49 |
Dynamic Cost in Rs crore: |
3.68 |
Contractor Details |
Mohammad Ali |
Date of Signing of Contract |
24 April 2008 |
Date of Start of Work (NTP) |
30 May 2008 |
Completion Period |
(9 Months) |
Completion Date as per Contract |
28 February 2009 |
|
|
|
Project completed and handed over to PWD (R&B) Deptt Kargil
|
|
|